> First we need to find out the concrete work volume
Hold on,
Length = 40 feet
Width = 20 feet
Thinness = 5 inches
Wet volume = (40 * 20 * 5/12) or 333.33 cubic feet
[To split in inches to be shared by 12]
> Wet size will be multiplied by 1.55 times to get wet size.
Dry size = (333.33 * 1.55) or 516.66 cubic feet
> Now the sum of the concrete mixing ratio is to be found.
Hold on,
Ratio = 1: 2: 4
Sum = (1 + 2 + 4) or 7